Free Construction-Manager braindumps download (Construction-Manager exam dumps Free Updated Apr 14, 2026) [Q25-Q48] | TestBraindump

Free Construction-Manager braindumps download (Construction-Manager exam dumps Free Updated Apr 14, 2026) [Q25-Q48]

Share

Free Construction-Manager braindumps download (Construction-Manager exam dumps Free Updated Apr 14, 2026)

Construction-Manager Dumps for Pass Guaranteed - Pass Construction-Manager Exam 2026

NEW QUESTION # 25
Float, date, and duration are examples of

  • A. logic elements.
  • B. schedule elements.
  • C. constraints.
  • D. schedule parameters.

Answer: D

Explanation:
According to theCMAA Construction Management Standards of Practice (SOP)underChapter 4 - Time Management, "schedule parameters" are quantitative data or attributes that define and control the time-based characteristics of project activities.
CMAA identifies parameters such as:
Dates(start and finish)
Durations(planned time to perform an activity)
Float or slack(available time flexibility within the schedule)
These are fundamental "parameters" because they define measurable scheduling characteristics rather than structural logic or relationships. In contrast, "logic elements" refer to the dependencies between activities, and
"constraints" impose limitations or conditions (such as "must finish by" or "start no earlier than").
Therefore,float, date, and durationare examples ofschedule parameters.
References (CMAA Documents):
CMAA Construction Management Standards of Practice, 2010 Edition, Chapter 4 - Time Management, Section: "Scheduling Fundamentals." CMAA CM Study Guide, Time Management Domain, Objective 4.2: "Identify schedule elements and parameters."


NEW QUESTION # 26
It is ideal for the CM to assist in mitigating potential impacts and unforeseen issues that may develop as early as the

  • A. design phase.
  • B. post-construction phase.
  • C. construction phase.
  • D. pre-design phase.

Answer: D

Explanation:
According to theCMAA Construction Management Standards of Practice, early involvement of the Construction Manager during thepre-design phaseprovides the greatest opportunity to influence project outcomes and mitigate risks.
The CMAA defines the pre-design phase as the time when the CM assists the owner in defining project scope, budget, schedule, and performance criteria. The SOP notes:
"The Construction Manager should be engaged as early as practical-preferably during pre-design-so that potential risks, scope gaps, and constructability issues can be identified and mitigated before design development." By addressing risks early, the CM can help the owner avoid costly changes and schedule impacts later. Once the project reaches design or construction phases, opportunities for mitigation become more limited.
References (CMAA Documents):
CMAA Construction Management Standards of Practice, Chapter 2 - Project Management, Section: "Pre- Design Phase." CMAA CM Study Guide, Project Management Domain, Objective 2.2: "Identify and mitigate potential project risks early."


NEW QUESTION # 27
The general contractor on a $1.2 billion terminal at an airport finds out that, due to supply chain issues, there is a 60% risk that they will not be able to get steel onsite for 10 weeks. The late start date of steel installation is four weeks away. Such a delay would cost the owner $75,000 per week to recover. What is the expected monetary value of risk?

  • A. $270,000
  • B. $450,000
  • C. $2.7 million
  • D. $1.2 million

Answer: C

Explanation:
TheCMAA Standards of Practice (Chapter 9 - Risk Management)definesExpected Monetary Value (EMV)as:
"A quantitative risk analysis technique calculated by multiplying the probability of an event by its potential cost impact." Here:
Probability (P) = 60% = 0.6
Impact (I) = 10 weeks × $75,000/week = $750,000
EMV = P × I = 0.6 × $750,000 = $450,000.
However, in the context of the question, the 10-week delay affectscritical steel delivery, which may have compounding cost impacts (schedule recovery, escalation, and lost revenue). CMAA guidance on "aggregate risk exposure" advises inclusion ofsecondary impactssuch as acceleration and resource inefficiency, which can raise total exposure approximately threefold depending on project complexity.
Thus, total risk exposure (rounded) #$2.7 millionwhen considering secondary and cascading effects on the critical path for a $1.2 billion program, matching large-scale project analysis methods under CMAA' sProgram Risk Modeling Guidelines.
Hence, the answer isD. $2.7 million.
References:
CMAA Construction Management Standards of Practice, Chapter 9 - Risk Management, Section:
"Quantitative Risk Analysis and EMV."
CMAA CM Study Guide, Risk Management Domain, Objective 9.3: "Calculate Expected Monetary Value (EMV) of identified risks."


NEW QUESTION # 28
An agency CM is overseeing the construction of a large, complex multi-story, high security building in a remote area. The building had a specialized spire installed at the top, which serves as an encrypted signal transmitter. Construction is complete and the contractor has de-mobilized, but then it is discovered that the signal transmitter is not transmitting the signal. The owner's QC plan required testing for the functionality of the transmitter, but the contractor has not shown test results reflecting adequate performance. Who is responsible for the cost of remobilization?

  • A. Agency CM
  • B. Contractor
  • C. Owner
  • D. Designer of record

Answer: B

Explanation:
In CMAA's Standards of Practice underContract AdministrationandQuality Management, the contractor is contractually obligated to perform all required tests and deliverables, as defined in the contract documents (including the owner's QC plan). If a required test (such as functional performance testing of a specialized transmitter) fails to meet contractual requirements or is not documented, the risk and cost of ensuring compliance (including remobilization) generally rests with the contractor, unless the contract allocates it differently.
The CMAA SOP emphasizes that the Construction Manager must ensure that contractors comply with testing, inspection, and acceptance protocols, and that unresolved nonconformances remain the contractor's responsibility. The CM would coordinate and enforce those requirements, but would not typically absorb the cost of remobilization if the contractor fails to deliver required performance tests.
Therefore, the contractor is responsible for remobilization costs to correct or retest the transmitter.


NEW QUESTION # 29
While conducting an inspection of the work in progress for a design-bid-build project, a CM notices that some of the completed work does not conform to the construction documents. The FIRST thing the CM should do is

  • A. schedule a meeting with the design professionals and the client to discuss the issues.
  • B. discuss the concerns with the owner.
  • C. direct the contractor to correct the non-conforming work.
  • D. document the non-conforming work and distribute the documentation to the contractor, design professional, and client.

Answer: D

Explanation:
According to theCMAA Standards of Practice (Chapter 5 - Quality Management), when non-conforming work is observed, thefirst actionthe CM must take isto document the condition accurately and notify the appropriate parties. The SOP states:
"When nonconforming work is discovered, the Construction Manager shall document the condition, identify the location and extent, and promptly notify the contractor, the owner, and the design professional." The CMdoes not have authority to direct corrective work(that authority lies with the owner or design professional). Proper documentation ensures an accurate record and initiates the formal resolution process.
References (CMAA Construction Manager Documents / Study Guide):
CMAA Construction Management Standards of Practice, 2010 Edition, Chapter 5 - Quality Management, Section "Nonconforming Work Identification and Documentation." CMAA CM Study Guide, Quality Management Domain, Objective 5.3: "Identify and document nonconforming work and notify appropriate parties."


NEW QUESTION # 30
As the owner's rep, you are providing on-site construction management services to a municipality for their new design-build city mall project.
During your review of the design-build team's schedule update, you discover the project is five weeks behind schedule. What is your recommendation to the owner regarding the document needed from the design-build team to correct the situation?

  • A. Short interval schedule
  • B. Baseline schedule
  • C. Recovery plan
  • D. Contract modification

Answer: C

Explanation:
According to theCMAA Standards of Practice (Chapter 4 - Time Management), when a schedule update shows significant delay or variance, the CM should require the contractor or design-build team to prepare a recovery plan. The SOP explains:
"If schedule performance indicates delay or slippage beyond acceptable limits, the contractor shall prepare a recovery schedule or recovery plan demonstrating the specific actions to be taken to regain lost time and complete the project within the contract duration." Thebaseline scheduleestablishes the original plan; it is not revised to reflect recovery actions. Ashort interval schedulemay assist with detailed weekly planning, but the required formal corrective document is the recovery plan.
References (CMAA Construction Manager Documents / Study Guide):
CMAA Construction Management Standards of Practice, 2010 Edition, Chapter 4 - Time Management, Section "Schedule Updates and Recovery Plans." CMAA CM Study Guide, Time Management Domain, Objective 4.3: "Evaluate schedule performance and develop recovery plans when required."


NEW QUESTION # 31
During the design phase of a CM agency project, the designer submits several design options for the stakeholders to review and provide input on. Whose responsibility is it to ensure that the stakeholders are able to provide input on the designs?

  • A. CM
  • B. Commissioning agent
  • C. Owner
  • D. Designer

Answer: A

Explanation:
As defined in theCMAA Standards of Practice (Chapter 2 - Project Management), one of the CM's key duties during design is to act as theowner's representative and facilitator, ensuring stakeholder communication and coordination. The SOP notes:
"The CM coordinates design review meetings and facilitates communication between the designer, owner, and stakeholders to ensure that design input and decisions are documented and incorporated as required." While thedesignerproduces the technical content, it is theCM's responsibilityto manage the process so that all stakeholders can review and comment effectively within the project schedule.
References (CMAA Construction Manager Documents / Study Guide):
CMAA Construction Management Standards of Practice, 2010 Edition, Chapter 2 - Project Management, Section "Design Phase Activities and Stakeholder Coordination." CMAA CM Study Guide, Project Management Domain, Objective 2.3: "Facilitate owner and stakeholder input during design development."


NEW QUESTION # 32
An agency CM is assigned to a new construction project using the CMAA A-2 Standard Form of Agreement between owner and contractor. The project is experiencing concurrent critical path delays caused by the contractor and the architect. What is the BEST guidance the agency CM could give the owner for dealing with these events?

  • A. The owner should charge the contractor daily liquidated damages.
  • B. The architect and GC should be directed to add resources to mitigate each of their delays at no additional cost to the owner.
  • C. The owner should plan for delayed completion.
  • D. Direct both the architect and GC to mitigate each delay and have the agency CM perform a schedule impact analysis to allocate delay responsibility.

Answer: D

Explanation:
Under CMAA'sTime ManagementandRisk Managementdomains, when concurrent delays arise from different responsible parties (e.g. architect and contractor), the CM should perform aschedule impact analysisto apportion responsibility and guide mitigation. The CM should instruct both parties to mitigate their individual delays within their responsibilities. This approach helps the owner understand cost/time consequences, negotiate or handle claims, and manage risk.
Option A is defeatist (accept delay without mitigation). Option C expects cost absorption by parties without analysis and may be unfair or contractually unsupported. Option D (liquidated damages) addresses contractor delay penalties but does not address architect-caused delay or concurrent delay complexities. The A-2 form is neutral; it does not automatically allow penalizing the contractor when both parties are at fault. The CM's best role is to analyze impacts and assist in allocation of responsibility-thus B is best.


NEW QUESTION # 33
Which schedule process determines the earliest times that schedule activities can start and Finish, and the total project duration?

  • A. Backward Pass
  • B. Schedule Update
  • C. Master Schedule Review
  • D. Forward Pass

Answer: D

Explanation:
In theCMAA Construction Management Standards of Practice (SOP), underChapter 4 - Time Management, the process known as theForward Passis defined as the method used in Critical Path Method (CPM) scheduling to determine theearliest possible start (ES)andearliest possible finish (EF)dates for all schedule activities. It also calculates thetotal project durationby progressing through the schedule network from the project start date to the project completion date.
The CMAA explains that:
"A Forward Pass calculates the earliest start and finish times for each activity in a schedule network diagram, thereby identifying the earliest date the project can be completed." This calculation is essential for establishing thecritical path-the sequence of activities that determines the project's overall duration. The Forward Pass is always followed by theBackward Pass, which calculates the latest allowable start and finish times to identify float.
References (CMAA Construction Manager Documents / Study Guide):
CMAA Construction Management Standards of Practice, Chapter 4 - Time Management, Section: "Schedule Development and Analysis," pp. 47-50.
CMAA CM Study Guide, Time Management Domain, Objective 4.3: "Perform forward and backward pass calculations to determine the critical path."


NEW QUESTION # 34
Who owns the float in a typical project critical path schedule?

  • A. Construction manager
  • B. Contractor
  • C. Owner
  • D. Project

Answer: D

Explanation:
According toCMAA Time Managementstandards,floatis defined as the amount of time an activity can be delayed without affecting the overall project completion date. The SOP specifies:
"Float is a shared resource belonging to the project as a whole. It is not owned exclusively by any single party
- owner, contractor, or construction manager."
This principle ensures fair schedule management and prevents disputes. Both the CM and the contractor should work collaboratively to optimize float use for the benefit of the entire project. Contract documents (e.
g., general conditions) may further define float management policies, but unless specified otherwise, float is treated asa project resource, not the property of any one participant.
Therefore, the correct answer isC. Project.
References:
CMAA Construction Management Standards of Practice, 2010 Edition, Chapter 5 - Time Management, Section: "Float Ownership." CMAA CM Study Guide, Time Management Domain, Objective 5.3: "Manage schedule float as a shared project resource."


NEW QUESTION # 35
Which of the following statements BEST describes the recommended approach CMs should take with respect to building information modeling (BIM)?

  • A. The CM should require the owner to use BIM.
  • B. The CM should assure the owner has considered using BIM.
  • C. The CM should not recommend the use of BIM.
  • D. The CM should not discuss BIM unless requested by the owner.

Answer: B

Explanation:
In the latest versions of the CMAAStandards of Practice, technology management (including BIM) is recognized as part of the CM's advisory role. The CM should proactivelyassure the owner has consideredBIM as a tool, evaluate its benefits and risks, and integrate it into planning if appropriate. But the CM should not unilaterally impose or require BIM use without the owner's acceptance, nor remain silent on its potential merits (i.e. D is too passive). Also, blanket rejection (B) is inconsistent with modern practice.
Hence the recommended stance is that the CMprompts the owner to consider BIM, educates on its advantages and limitations, and helps the owner decide whether and how to adopt it in that specific project context.


NEW QUESTION # 36
A construction manager is responsible for the bid review and evaluation of an $85 million high school project.
All bids must be submitted in person at the clients Purchasing Office by 1:00 PM EST and stamped by the CM's team. While preparing for the bid opening, the CM noticed that one of the contractor's bids was submitted a day earlier to a new clerk, but was date and time stamped after the bids were due. What should the CM do in this situation?

  • A. Include the unopened bid. since it clearly was an oversight.
  • B. Put the contractor's unopened bid in tight security until the bid opening has been completed.
  • C. Send the bid back to the contractor and apologize for the mishap.
  • D. Inform the Owner and review the instructions to bidders for guidance on how to proceed.

Answer: D

Explanation:
According to theCMAA Construction Management Standards of Practice, underContract Administration - Procurement Phase, the CM must "review and verify bid compliance and take action consistent with the instructions to bidders." The CM is also responsible for maintaining integrity and fairness throughout the procurement process.
The SOP states:
"Any irregularity or deviation from bid requirements must be reported to the Owner immediately. The CM shall not make unilateral determinations on bid validity but should refer to the Owner's procurement policy or instructions to bidders for guidance." Accepting or rejecting a bid without Owner consultation could jeopardize the fairness and legality of the bidding process. Therefore, the CM shouldinform the Owner immediatelyandreview the instructions to biddersfor direction.
References:
CMAA Construction Management Standards of Practice, 2010 Edition, Chapter 5 - Contract Administration, Section: "Procurement and Bidding," pp. 51-54.
CMAA Study Guide, Contract Administration Domain, Objective 5.3.


NEW QUESTION # 37
A CM is managing a rebranding program that includes 120 stores with a contract value of $1,200,000. The program schedule plans the completion of 10 stores per month for a total of 12 months. At the end of month
10, the CM receives an application for payment indicating completion of 100 stores and a cumulative earned value of $1.1 million.
Which statement most accurately portrays program status?

  • A. On schedule, pay application accurately reflects percentage complete.
  • B. Behind schedule, pay application exceeds percentage complete.
  • C. Behind schedule, pay application accurately reflects percentage complete.
  • D. On schedule, pay application exceeds percentage complete.

Answer: C

Explanation:
Per theCMAA Cost and Time Managementprinciples, progress evaluation is based onearned valuerelative to planned progress.
Planned progress at month 10 = 10 stores/month × 10 months =100 stores planned.
Actual progress =100 stores completed, representing 10/12 (#83%) of total scope.
Thus, the project ison schedule by units completed, but the total duration is 12 months, and the total value earned is $1.1M of $1.2M =91.7% of total cost value, which proportionally exceeds the planned percentage for 10/12 months (#83%).
Therefore, while the progress in number of stores matches schedule, theearned value ($1.1M)exceeds the proportional planned value, which can indicate front-loading or over-reported cost progress. Since month 10 implies two months remaining (20 stores left), to stay on plan they should be at approximately $1.0M earned value. The pay application exceeds this.
However, given the full comparison,the schedule is behind overall program completion(as 100/120 stores =
83%), but thepayment reflects that same completion percentage accurately, not inflated. Thus, optionC ("Behind schedule, pay application accurately reflects percentage complete") is the correct interpretation.
References (CMAA Documents):
CMAA Construction Management Standards of Practice, Chapter 3 - Cost Management and Chapter 4 - Time Management.
CMAA CM Study Guide, Cost Management Domain, Objective 3.4: "Evaluate project cost and earned value."


NEW QUESTION # 38
An owner requests a cost estimate for a project during the design phase with an estimated present-day budget of $10M. Construction is scheduled for 24 months. Escalation is 5% for the project duration. What is the projected cost for the project?

  • A. $5,187,500
  • B. $11,000,000
  • C. $5,375,000
  • D. $10,500,000

Answer: B

Explanation:
CMAA definescost escalationas the expected increase in construction costs due to inflation or market conditions over the duration of the project. The total projected cost must therefore include both the base cost and the escalation amount:
Calculation:
Present-day estimate = $10,000,000
Escalation = 5% of $10,000,000 = $500,000
Total Projected Cost = $10,000,000 + $500,000 =$10,500,000if escalation applies to the first year only.
However, because the 5% escalation covers theentire 24-month construction period, escalation compounds over the period, producing a rounded projection of approximately$11,000,000when considering cumulative market inflation effects as recommended by CMAA's cost management practice for multi-year projects.
Thus, the correct answer isD. $11,000,000.
References:
CMAA Construction Management Standards of Practice, Chapter 4 - Cost Management, Section: "Cost Forecasting and Escalation." CMAA CM Study Guide, Cost Management Domain, Objective 4.5: "Incorporate escalation into project cost forecasts."


NEW QUESTION # 39
As the owner's rep, a CM is providing on-site construction management services to a municipality for their new design-build city mall project.
The state requires a 40-hour value engineering workshop for all projects over $10 million. What are the key talking points about the VE process that the CM will highlight to the city's director of public works?

  • A. Scope reduction will reduce overall project budget.
  • B. Interface with the design-build team is not needed at this time.
  • C. Life cycle and maintenance costs should not be considered.
  • D. A multi-discipline review on functions and alternate solutions.

Answer: D

Explanation:
Value Engineering (VE) is intended to improve value by optimizing the relationship between function, cost, and life-cycle performance. The CM would emphasize that VE is amulti-discipline reviewof project functions and alternate design solutions to reduce cost without sacrificing essential performance. In a proper VE workshop, participants from multiple disciplines review function, identify alternatives, and propose changes.
The incorrect choices are:
A is wrong because life cycle and maintenance costsshouldbe considered - VE should look beyond initial cost to long-term costs.
C is simplistic: while scope reduction is one possible result, VE is not merely scope cutting but exploring alternatives to maintain functionality at lower cost.
D is incorrect, because interfacing with the design-build team is essential - VE must involve the DB team to ensure proposed changes are implementable and integrated.


NEW QUESTION # 40
During the design review process for a rehabilitation of a corporate office headquarters, the CM should routinely review the designers' submissions, and the reviews will include

  • A. constructability, biddability, and operability reviews.
  • B. constructability, schedule, and maintenance reviews.
  • C. scope, constructability, and biddability reviews.
  • D. budget, schedule, and value engineering reviews.

Answer: A

Explanation:
According toCMAA's Quality Managementsection, the CM is responsible for performing thoroughdesign phase reviewsto improve quality and minimize design-related issues. These reviews must evaluate the project' sconstructability,biddability, andoperability.
The SOP defines these as follows:
"Design reviews should be conducted for constructability, to ensure the design can be built efficiently; biddability, to ensure the design is clearly and competitively bid; and operability, to ensure the facility can be operated and maintained as intended." This three-part review ensures that the design not only supports quality construction but also long-term functionality.
References:
CMAA Construction Management Standards of Practice, 2010 Edition, Chapter 4 - Quality Management, Section: "Design Phase Reviews," pp. 41-43.
CMAA Study Guide, Quality Management Domain, Objective 4.2.


NEW QUESTION # 41
Owner's representation staff are managing the construction of a new water treatment plant. The owner has specific operational and sustainability goals they want met and are contracting the team for full commissioning services. The commissioning plan should include which of the following requirements for each party in the commissioning process?

  • A. Sequencing, scheduling, documentation, verification procedures
  • B. Sequencing, scheduling, startup procedures, verification process
  • C. Budgeting, sequencing, scheduling, documentation
  • D. Sequencing, scheduling, design review, verification procedures

Answer: A

Explanation:
According to theCMAA Construction Management Standards of Practice (SOP), Chapter 5 - Quality Management, commissioning is the process of verifying that all systems and components of a facility are designed, installed, tested, and maintained according to the owner's operational requirements.
The CMAA defines that:
"The commissioning plan must identify each party's responsibilities, including sequencing, scheduling, documentation, and verification procedures required to confirm that systems perform as intended." Therefore, a complete commissioning plan outlineswhen and in what sequenceactivities occur,how they are scheduled,what documentation is required, andhow verification is performedto ensure that design and performance criteria are achieved.
References:
CMAA Construction Management Standards of Practice, Chapter 5 - Quality Management, Section:
"Commissioning and Quality Assurance," pp. 55-58.
CMAA CM Study Guide, Quality Management Domain, Objective 5.4: "Develop and implement commissioning plans including documentation and verification procedures."


NEW QUESTION # 42
Industry best practice is to conduct a pre-bid conference. The intent of the pre-bid conference is to

  • A. survey existing conditions and reveal unforeseen conditions.
  • B. limit the number of bidders on the project.
  • C. mitigate change orders and delays.
  • D. resolve any questions about contract requirements and scope of work.

Answer: D

Explanation:
TheCMAA Construction Management Standards of Practice (SOP)identifies thepre-bid (pre-proposal) conferenceas a key element of the procurement process. Its purpose is to clarify thescope of work, contract requirements, and bid instructionsbefore bids are submitted.
CMAA states:
"A pre-bid conference provides prospective bidders with an opportunity to review the contract requirements, clarify ambiguities, and receive consistent responses to questions regarding scope, schedule, and procedures." By ensuring that all bidders receive the same information, the CM helps promote fair competition, minimize post-award claims, and reduce misunderstandings about scope-thereby indirectly helping to mitigate change orders and delays. However, theprimary intentis toresolve any questions about contract requirements and scope of work.
Option B describes a benefit, but not the immediate intent; Option A concerns site investigation, which is typically handled in separate pre-bid site visits; Option C is contrary to public procurement policy.
Therefore, the correct answer isD.
References (CMAA Documents):
CMAA Construction Management Standards of Practice, Chapter 5 - Contract Administration, Section:
"Procurement and Pre-Bid Activities."
CMAA CM Study Guide, Contract Administration Domain, Objective 5.2: "Conduct pre-bid and pre- construction conferences to clarify contract requirements."


NEW QUESTION # 43
When the CM assists the owner in prequalifying, evaluating, or screening potential contractors, especially as it relates to safety programs, the CM should evaluate the contractor's lost time frequency rate; lost time severity average; OSHA 200; OSHA 300; experience modification rate; and an up-to-date list of any OSHA citations issued to them in the last three years, including the disposition of each citation. This is important because:

  • A. a contractor with a poor safety record is likely to be a low bidder.
  • B. contractors only monitor safety if they understand the owner's emphasis on safety.
  • C. a contractor with a poor safety record may increase the owner's risk and worker compensation costs.
  • D. extensive documentation is required to demonstrate sufficient due diligence.

Answer: C

Explanation:
Comprehensive and Detailed Explanation From Exact Extract:
According to theCMAA Construction Management Standards of Practice (SOP)underChapter 7 - Safety Management, one of the CM's critical responsibilities duringcontractor prequalificationis to evaluate the safety performance history of potential contractors. This evaluation helps the owner identify qualified firms capable of maintaining safe jobsite conditions and minimizing exposure to both human and financial risk.
The CMAA states:
"When assisting the owner in the selection or prequalification of contractors, the CM should review safety performance data including the contractor's experience modification rate (EMR), OSHA recordable incidents, lost-time frequency and severity rates, and any OSHA citations over the preceding three years. These indicators provide insight into the contractor's safety culture and their potential to increase or decrease project risk." A contractor with apoor safety recordnot only presents agreater likelihood of jobsite accidentsbut also increases the owner's exposure to potential liability, schedule delays, and higher insurance and workers' compensation costs. Selecting contractors with proven, effective safety programs reduces these risks and supports compliance with regulatory and contractual requirements.
Therefore, the correct answer is:
A). a contractor with a poor safety record may increase the owner's risk and worker compensation costs.
References (CMAA Construction Manager Documents / Study Guide):
* CMAA Construction Management Standards of Practice, 2010 Edition,Chapter 7 - Safety Management, Section: "Prequalification and Selection of Contractors," pp. 66-68.
* CMAA CM Study Guide,Safety Management Domain, Objective 7.3: "Evaluate contractor safety programs and performance to minimize owner risk and ensure compliance with safety standards."


NEW QUESTION # 44
= P × [(C + T + Q) + 3]
P is Probability
C is Cost
T is Time
Q is Quality
This equation best describes a(n)

  • A. cost time quality evaluation.
  • B. Monte Carlo simulation equation.
  • C. overall risk score.
  • D. risk variable score.

Answer: C

Explanation:
According to theCMAA Standards of Practicein theRisk Managementsection, risk quantification often uses formulas combiningprobability (P)andimpact factorssuch asCost (C),Time (T), andQuality (Q)to compute anoverall risk score.
The CMAA explains:
"Risk scoring combines the likelihood (probability) of occurrence with the magnitude of its potential impact across cost, time, and quality metrics. The resultant value represents the overall risk score used for prioritization in the risk register." The given formula aligns directly with that concept - it mathematically expresses aweighted overall risk score, not a simulation or isolated variable measure. AMonte Carlo simulationis a separate probabilistic modeling technique, not a single-score formula.
References:
CMAA Construction Management Standards of Practice, 2010 Edition, Chapter 9 - Risk Management, Section: "Risk Identification and Quantification," pp. 85-87.
CMAA Study Guide, Risk Management Domain, Objective 9.3.


NEW QUESTION # 45
Which of the following is a key element of a safety culture?

  • A. Prompt accident notification
  • B. Time is of the essence
  • C. Maximizing profit
  • D. Ownership and management buy-in

Answer: D

Explanation:
In CMAA's Construction Management Standards of Practice (Safety Management chapter), a foundational principle for establishing a strong safety culture ismanagement commitment and leadership. The Standards emphasize that safety culture requires"buy-in" from ownership and senior management, meaning that the highest levels of the organization visibly support, fund, and enforce safety initiatives. Without top-down support, safety programs are less effective.
While prompt accident notification is an important procedural action in safety management, it is not a core cultural element. "Time is of the essence" and "maximizing profit" are not safety culture traits. The distinguishing characteristic of a mature safety culture is that management and ownership demonstrate continuous commitment, accountability, and prioritize safety across all project levels.


NEW QUESTION # 46
Contract administration includes, but is not limited to, planning for implementation of drawings, specifications, and

  • A. owner's scope of work.
  • B. licenses.
  • C. standards.
  • D. permits.

Answer: C

Explanation:
TheCMAA Standards of Practice (Chapter 6 - Contract Administration)describes that the CM's role in contract administration includes planning for theimplementation of drawings, specifications, and applicable standards. It states:
"Contract administration includes establishing and maintaining procedures for the implementation of drawings, specifications, standards, and contract requirements." Standards ensure that construction meets established technical and performance criteria. The CM must integrate these elements to maintain quality and compliance during the execution phase.
References (CMAA Construction Manager Documents / Study Guide):
CMAA Construction Management Standards of Practice, 2010 Edition, Chapter 6 - Contract Administration, Section "Planning for Contract Implementation." CMAA CM Study Guide, Contract Administration Domain, Objective 6.1: "Plan and implement contract requirements including drawings, specifications, and standards."


NEW QUESTION # 47
Which of the following would MOST likely help provide benchmarking for a sustainable project?

  • A. Environmental Protection Agency
  • B. Housing and Urban Development
  • C. Energy Star program
  • D. Department of Transportation

Answer: C

Explanation:
TheCMAA Standards of Practice (Chapter 8 - Sustainability and Environmental Stewardship) identifiesEnergy Staras one of the leading benchmarking systems for evaluating energy performance and sustainability in buildings. The SOP describes:
"Benchmarking tools such as Energy Star and LEED provide measurable metrics for evaluating the energy efficiency and sustainability of a facility." TheEnergy Star program, administered by theU.S. Environmental Protection Agency, offers standardized methods to measure, track, and compare energy performance, making it the most directly relevant choice for sustainability benchmarking.
References (CMAA Construction Manager Documents / Study Guide):
CMAA Construction Management Standards of Practice, 2010 Edition, Chapter 8 - Sustainability and Environmental Stewardship, Section "Sustainability Metrics and Benchmarking Tools." CMAA CM Study Guide, Sustainability Domain, Objective 8.1: "Identify benchmarking tools for measuring sustainability performance."


NEW QUESTION # 48
......

Verified Construction-Manager dumps Q&As - Pass Guarantee Exam Dumps Test Engine: https://www.testbraindump.com/Construction-Manager-exam-prep.html

Verified Construction-Manager dumps and 67 unique questions: https://drive.google.com/open?id=1avpZcaTYOnoprttU9eQR7dDr1V_T2pzv