[Dec 21, 2021] Latest C_TSCM42_67 Exam with Accurate SAP Certified Application Associate - Production Planning & Manufacturing with SAP ERP 6.0 EHP7 PDF Questions
Practice To C_TSCM42_67 - TestBraindump Remarkable Practice On your SAP Certified Application Associate - Production Planning & Manufacturing with SAP ERP 6.0 EHP7 Exam
SAP PP Certification Exam Topics:
| Topic Areas | Topic Details, Courses, Books | Weighting |
|---|---|---|
| Production Orders Advanced (PP-SFC) | Configure production order functionality. SCM310 OR TSCM40, TSCM42 | > 12% |
| Master Data (LDM) | Set up master data for production planning and manufacturing. PLM114 OR TSCM40, TSCM42 | 8% - 12% |
| Process Orders (PP-PI) | Identify specific properties of process orders. SCM300, SCM130 OR TSCM40, TSCM42 | < 8% |
| Basics on SAP Business Processes (E-Learnings) | Outline the scope of SAP SCM business processes. TERP01, TERP50 OR TSCM40, TSCM42 | < 8% |
| Material Requirements Planning (PP-MRP) | Explore material requirements planning functions. SCM240 OR TSCM40, TSCM42 | > 12% |
| Production Orders Basics (PP-SFC) | Apply production order functionality. SCM310 OR TSCM40, TSCM42 | 8% - 12% |
| Lean Manufacturing (PP-REM, PP-KAB) | Outline the highlights of repetitive manufacturing and kanban. SCM300, SCM130 OR TSCM40, TSCM42 | 8% - 12% |
| Application Overview and Background | haracterize the interplay of master data, planning, ATP, and production functionality. TERP50, SCM240, SCM300, SCM130ORTSCM40, TSCM42 | < 8% |
| Material and Capacity Requirements Planning | Characterize production-relevant planning functionality. SCM240, SCM365 OR TSCM40, TSCM42 | > 12% |
NEW QUESTION 29
Which function is supported by production orders?
- A. Automatic creation of transfer orders at order release
- B. Automatic selection of a work center at order release
- C. Automatic printing of order documents at order creation
- D. Automatic reading of PP master data at order release
Answer: A
NEW QUESTION 30
When maintaining a work center, formulas can be assigned in the scheduling view. Formulas use formula parameters for calculation.
What can be the origin of the formula parameters used for scheduling? (Choose three)
- A. Standard values in the operations of routings
- B. General values from work scheduling view of the material master
- C. User-defined fields in the operation of routings
- D. General item values of bill of materials
- E. General operation values of routings
Answer: A,C,E
NEW QUESTION 31
Which of the following structural elements does a process order have? (Choose three.)
- A. Phases
- B. Relationships
- C. Characteristic-based process instructions
- D. Item data
- E. Parallel sequences
Answer: A,B,C
NEW QUESTION 32
Which of the following scheduling types can only be used in capacity planning?
- A. Forward
- B. Only capacity requirements
- C. Backward
- D. Midpoint
Answer: D
NEW QUESTION 33
You select the master data for production orders via production versions.
Which information is contained in a production version?
- A. The control parameters for selecting routings and BOM
- B. The explosion dates for the routing and BOM
- C. The routing and BOM alternatives to be used
- D. The default order type to be used
Answer: C
NEW QUESTION 34
Which of the following master data can be used with process orders? (Choose three)
- A. Master recipes
- B. Serial numbers
- C. Resources
- D. Production versions
- E. Production/resource tools
Answer: A,C,D
NEW QUESTION 35
In which of the following objects can you activate backflushing of components if you want to use this functionality during order confirmation? (Choose three.)
- A. Routing
- B. Work Center
- C. Material Master (Finished Product)
- D. Production Scheduling Profile
- E. Material Master (Component)
Answer: A,B,E
NEW QUESTION 36
You want to create a new material that - is kept in stock- is externally procured- is used as a component in the bills of material for various final products- must not be sold directly Which standard SAP material type do you use?
- A. ROH (raw material)
- B. NLAG (non-stock material)
- C. HAWA (trading good)
- D. FERT (finished product)
Answer: A
NEW QUESTION 37
Which of the following statements about the SAP Solution Manager listed is correct?
- A. Solution Manager is a stand-alone system that communicates with other systems in a system landscape.
- B. Solution Manager is an add-on industry solution.
- C. Solution Manager is part of the SAP ECC System.
- D. Solution Manager is a satellite system in a system landscape.
Answer: A
NEW QUESTION 38
What do you have to consider, when you use the ATP (Available To Promise) checks for material? (Choose two)
- A. ATP checks can be adjusted to also consider future requirements and receipts.
- B. ATP checks are automatically performed during Material Requirements Planning (MRP) runs.
- C. ATP checks are used to evaluate the free capacity on a certain work center.
- D. ATP checks are mandatory for lead-time scheduling.
- E. ATP checks can be carried out automatically when releasing a production order.
Answer: A,E
NEW QUESTION 39
Which property applies for consumption with planning strategy 40 (planning with final assembly)?
- A. Consumption takes place with the planning material.
- B. Consumption can reduce the originally planned production quantity.
- C. Consumption creates a static and binding assignment between the planned independent requirements and the customer requirements for the entire procurement process.
- D. Consumption can result in subsequent adjustments of planned receipts.
Answer: D
NEW QUESTION 40
What data can be posted directly via the Plant Data Collection (PP-PDC) interface?
- A. Confirmations
- B. Goods issues
- C. Maintenance notifications
- D. Goods receipts
Answer: A
NEW QUESTION 41
You have maintained planning strategy group 10 (make-to-stock production) in the material master (SAP ECC) of a material. For the coming months, you have planned requirements with requirement type LSF (derived from main strategy 10). Now, you want to change the requirement type from LSF to VSF (in accordance with planning strategy 40, planning with final assembly) for requirements in the existing production plan.
Which of the following scenarios are applicable in this case? (Choose two)
- A. You must change the requirement type for planning strategy 10 to VSF in Customizing. The requirement type for all existing requirements is then changed by the next planning run.
- B. You can change the strategy group from 10 to 40 for the existing production plan in the material master, and the requirement type for all requirements is changed automatically.
- C. You can enter the strategy group 40 in the material master, but the requirement type is not changed automatically for existing requirements.
- D. You can enter the strategy group 40 in the material master and change the present requirement for the product manually in the production plan.
Answer: C,D
NEW QUESTION 42
What do you have to consider regarding lot size procedures?
- A. If a make-to-order production strategy is used, only the lot-for-lot (exact) lot size can be applied.
- B. The lot size quantity can be influenced using a minimum lot size and the rounding profile.
- C. If a long-term lot size is used, procurement is conducted with a long-term perspective.
- D. The procurement quantity of a lot size procedure can be specified using a safety time period profile.
Answer: B
NEW QUESTION 43
Your customer does not want to manage value-intensive materials in the warehouse. These materials should be procured directly for the production order.
Which BOM item category must you set to fulfill this requirement?
- A. E (external procurement)
- B. N (non-stock item)
- C. D (document item)
- D. M (phantom material)
Answer: B
NEW QUESTION 44
What is SAP Solution Manager?
- A. A transaction in the SAP ECC system
- B. A standalone system that communicates with other systems in a system landscape
- C. An add-on industry solution
- D. A managed system in a system landscape
Answer: B
NEW QUESTION 45
Which of the following properties about the planning functions available in SAP ECC applies?
- A. In demand management (DM) material shortage situations are identified and corresponding receipt elements are created.
- B. Master production scheduling (MPS) refers to preferred planning of important materials.
- C. Long-term planning (LTP) is a long-term form of forecasting.
- D. Material requirements planning (MRP) includes automatic capacity leveling.
Answer: B
NEW QUESTION 46
Which of the following activities within the KANBAN procedure normally triggers subsequent stock posting of the goods receipt?
- A. Set "Container in process"
- B. Set "Container in transport"
- C. Set "Container empty"
- D. Set "Container full"
Answer: D
NEW QUESTION 47
When analyzing the SAP ECC order report for a planned order for a finished product, you discover that one of the assemblies will not be available in time for the scheduled final assembly because of automatic forward scheduling.
Which planning procedure do you use to create a feasible production plan from a requirements planning perspective?
- A. Multi-level single-item planning with the "simulation mode" option
- B. Total planning online
- C. Interactive single-item planning for the delayed assembly
- D. Multi-level single-item planning with the "display material list" option
Answer: A
NEW QUESTION 48
......
C_TSCM42_67 Exam Certification Details:
| Exam: | 80 questions |
| Component: | Production Planning |
| Sub-solution: | Product Developmement & Manufacturing |
| Sample Questions: | SAP C_TSCM42_67 Exam Sample Question |
| Level: | Associate |
| Cut Score: | 63% |
| Duration: | 180 mins |
| Languages: | German, English, Japanese |
Exam Questions and Answers for C_TSCM42_67 Study Guide Questions and Answers!: https://www.testbraindump.com/C_TSCM42_67-exam-prep.html